# PERT estimate calculator > How long will your project really take? Turn best, likely and worst-case estimates into an expected time and a range you can trust. Calculate the PERT three-point estimate (O + 4M + P) / 6, the standard deviation and confidence ranges for one task or a chain of tasks added together. - Page: https://how.box/pert/ - Runs entirely in the browser. - License: HowToolbox's own text and data (titles, explanations, FAQs, tool descriptions and schemas, this file) are CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/); AI training and answers are welcome. Attribute "HowToolbox (how.box)" with a link to the page used. Third-party data keeps its own terms; the name and logo are not licensed. Publisher: HowToolbox, contact@how.box. Terms: https://how.box/about/terms/ ## Inputs Answer link: https://how.box/pert/?t={t}&u={u} - `t` (array): Tasks, versioned: ~1:id.optimistic.likely.pessimistic_…. Example: `[object Object],[object Object],[object Object]`. - `u` (h, d or wk): h, d or wk: the unit of the estimates. Example: `d`. Example answer: https://how.box/pert/?t=%7E1%3At1.2.4.8_t2.5.8.15_t3.2.3.6&u=d A complete link carries the primary answer in the page HTML; a missing or invalid value shows the default page. ## Agent tools - `pert_calculate`: Three-point (PERT) estimate for one or more tasks done in sequence. - MCP, one POST to https://how.box/mcp: `{"jsonrpc":"2.0","id":1,"method":"tools/call","params":{"name":"pert_calculate","arguments":{"tasks":[{"id":"t1","optimistic":2,"likely":4,"pessimistic":8},{"id":"t2","optimistic":5,"likely":8,"pessimistic":15},{"id":"t3","optimistic":2,"likely":3,"pessimistic":6}],"unit":"d"}}}` - GET: https://how.box/mcp/run/pert_calculate?tasks=%5B%7B%22id%22%3A%22t1%22%2C%22optimistic%22%3A2%2C%22likely%22%3A4%2C%22pessimistic%22%3A8%7D%2C%7B%22id%22%3A%22t2%22%2C%22optimistic%22%3A5%2C%22likely%22%3A8%2C%22pessimistic%22%3A15%7D%2C%7B%22id%22%3A%22t3%22%2C%22optimistic%22%3A2%2C%22likely%22%3A3%2C%22pessimistic%22%3A6%7D%5D&unit=d ## How it works A single estimate hides how uncertain it is. The three-point (PERT) estimate asks for a best case, a normal case and a worst case, and weights the normal case most. The result is an expected time that is more honest than a guess, plus a measure of how much it can vary. For optimistic O, most likely M and pessimistic P, the expected time is E = (O + 4M + P) ÷ 6 and the standard deviation is σ = (P − O) ÷ 6. For O = 2, M = 4 and P = 8 days, E = 26 ÷ 6 = 4.33 days and σ = 1. For tasks in a row, the expected times add up, and the variances (σ²) add up, so the total σ is the square root of that sum. About 68% of outcomes fall within E ± σ and 95% within E ± 2σ. Source: Wikipedia, "Three-point estimation". The ranges are an approximation that treats the tasks as independent and the total as a normal curve. If tasks run in parallel, only the longest path counts, so enter just that path. Estimates still depend on honest inputs: the formula cannot fix an optimistic worst case. ## FAQ **Why divide by 6 and weight the likely time by 4?** PERT approximates a beta distribution. Weighting the most likely time four times and each extreme once gives a mean close to that distribution, and the range from best to worst case covers about six standard deviations. **What is the difference between PERT and a simple average?** A simple average of the three numbers gives the extremes the same weight as the usual case. PERT trusts the most likely estimate more, so one wild worst-case number moves the result less. **How do I read the 68%, 95% and 99.7% ranges?** If your estimates were right, about 68% of the time the real total falls inside the first range, 95% inside the second and 99.7% inside the third. **What if tasks can run at the same time?** Enter only the tasks on the longest chain, the critical path. Tasks done in parallel do not add their times together. **Can I use it with money instead of time?** The maths works for any quantity with a best, likely and worst case, such as cost. The unit label only says days, hours or weeks, so ignore it and read the numbers as your own unit. More: [HowToolbox index](https://how.box/llms.txt) · [Agent Skill](https://how.box/skill.md) · [agent terms](https://how.box/about/agents/)